Te Puke, Bay of Plenty
Te Puke Wastewater Treatment Plant
1,145 m²
base slab
Two big pours with our 38 m booms, including a 1,145 m², 300 mm base slab poured from a 4 am start with two booms and two trucks at once.
Location
Te Puke, Bay of Plenty
Industry
Civil
Main contractor
McConnell Dowell
Completed
2026
Overview
Two booms, one base slab
Working alongside McConnell Dowell on critical wastewater infrastructure for the Western Bay, we pumped and placed two big pours with our 38 m booms.
The first was 1,361 m² of site concrete, about 200 m³. The second was a 1,145 m², 300 mm thick base slab (344 m³) with a U3 finish, poured from a 4 am start with two booms and two trucks running at once. We also poured an earlier 174 m², 120 mm site-office slab.